Latest plumbing details at Elite Tower in Zahraa El Maadi
- All riser works on the façades and light wells have been completed to the highest technical specifications.
All riser works on the façades and light wells have been completed to the highest technical specifications.
Waterproofing of internal bathrooms is underway:
1. A cement plaster layer.
2. A cold-applied waterproofing coat.
3. An Insumat membrane layer.
4. A cold-applied coating.
5. Covering with clean sand.
Installation of internal drainage is underway.